Packaging line PLC retrofit

Food packaging · obsolete PLC · 36-hour shutdown window

Situation

A Victorian food packaging site ran a cartoner and case packer on a controller family no longer supported by the OEM. Spare CPUs were exhausted globally; intermittent memory faults caused unplanned stops twice per month. Production demanded a retrofit inside a single planned hygiene shutdown—roughly thirty-six hours from electrical isolation to first salable pack.

Problems encountered

Engineering response

TECHNLOGIX PTY LTD reverse-engineered sequences by observing production runs and logging IO states during changeovers. We produced a state-based functional description signed by maintenance before any code was written. Safety functions were revalidated with the site’s WHS representative; hardwired e-stops remained hardwired, with PLC performing only documented monitoring functions.

Bench testing used a simulated IO rack mirroring address mapping. FAT included fault injection: jam sensors, missing product gaps, and reject gate failures. During shutdown, we migrated in slices—utilities and conveyors first, packaging heads second—so partial rollback remained possible until the final four hours.

Outcomes

Cutover completed inside the window with two minor punch items cleared during hypercare the following week. Unplanned stops tied to the old controller were not seen again over the next two quarters of operation. OEE improved modestly after changeover timeouts were re-tuned with operator input. Maintenance received annotated logic exports and an updated IO list matching field labels.

Lessons for similar sites

Shutdown windows do not forgive missing FAT evidence. Investing three weeks in simulation saved an estimated full shift of on-site debugging. Sites planning similar retrofits should inventory safety relay wiring before quoting—electrical surprises are the largest schedule risk.